Forum Discussion
Gantt activity duration
Thanks John for the response. Sorry for the poor information, I understand that there are many configurations in project and I have only recently started using it. Attached you will find a screenshot of what i mean. The activity duration is 1.56 days and in the gantt view it marks three days.
I think this happened because i started to change the calendar settings and the working hours.
My settings where:
- Calendar: Standard
- Start hour: 0:30
- End hour: 23:30
- Hours per day: 24
I started a new Project sheet and started from 0, every configuration as default and i didn't have a problem.
Thanks for your time and help, have a wonderful week!
Regards,
Renzo
Your calendar setting from 00:30 to 23:30 shows you have 23 hrs in a day not 24 hrs. So, when you enter 2 days (48 hrs), this shows up on Gantt over 2+ days, 23 hrs on 1st day, 23 hrs on 2nd day & 2hrs on 3rd day.
Either change your hours per day to 23 hrs or change your start time from 00:00 to 00:00.
=jerome