Fill in Project Start Date
What magic do I need to series fill a date? Like in Excel. I had to do manually.
For example:
Start |
Mon 10/11/21 |
Tue 10/12/21 |
Wed 10/13/21 |
Thu 10/14/21 |
Fri 10/15/21 |
Wayne
Sorry but Project does not have that feature. It could be done with a little VBA but that's it.
John
- John-projectSilver Contributor
Sorry but Project does not have that feature. It could be done with a little VBA but that's it.
John
- WayneDoubleuCopper ContributorYeeeesh. Thanks!
- John-projectSilver ContributorWayne,
You're welcome and thanks for the feedback.
I think the feature is appropriate in Excel because users are often creating spreadsheets with a consecutive dates, (I do that myself), but there are very few instances in a schedule where the dates are consecutive.
John