Exporting Project - Resource Usage table with phased time data to excel
I'm the John guy Dale referred to and yes I can help you with VBA to export Project timescaled data to Excel. I can write code to create the spreadsheet you show in your 2nd screen shot but I don't think that's really what you want. Look closely. The material resource "boiler floor space" shows 140 square meters which is correctly spread over 4 days in Project's Resource Usage view. Yet somehow, that 140 square meters has morphed into 175 square meters spread over 5 days on the Excel spreadsheet. Details, details.
I've done this very type of export for a ton of users and myself over the years. If you'd like my help with this, I suggest we work one-on-one via e-mail. I will ask some questions. My contact info is below.