Yes you can keep tasks for one or more resources from being leveled. Assuming you are using the stand alone desktop version of Project, you should see these options:
Hope this helps
John
- AlexTramacMay 24, 2023Copper ContributorHi John,
Everything looks to be leveled for everyone. If I want to take out only 1 person from the level, can I do it and if "yes", how?- John-projectMay 24, 2023Silver ContributorAlexTramac,
The easiest way to remove a specific resource from the leveling operation is to set the task or resource assignment priority to 1000. That essentially says, "don't level this assignment". Here's more information on that:
https://support.microsoft.com/en-us/office/priority-fields-096ac288-1507-431f-bc6f-5b8b3a6f2673
John