EST, LST, EFT AND LFT
Hey, Can I add in MS Project to the network diagram the 4 times for any activity? I mean: earliest start time, latest start time, earliest finish time and latest finish time thanks
- Dec 29, 2022
You mean something like this?
If so, select the Network Diagram view and then go to, Network Diagram Format > Format group > Format Box Styles. From there create your own template with the desired fields such as I've shown here: Note, for the label to show, click the "show label in cell box". For the data to show, do not click that box. (That may seem obvious but it took me a few minutes to figure out the "decoder key").
Hope this helps.
John
John-project
Dec 29, 2022Silver Contributor
You mean something like this?
If so, select the Network Diagram view and then go to, Network Diagram Format > Format group > Format Box Styles. From there create your own template with the desired fields such as I've shown here: Note, for the label to show, click the "show label in cell box". For the data to show, do not click that box. (That may seem obvious but it took me a few minutes to figure out the "decoder key").
Hope this helps.
John
Guy0956
Dec 30, 2022Copper Contributor
- John-projectDec 30, 2022Silver ContributorGuy0956,
You're welcome and thanks for the feedback.
John