Forum Discussion

Guy0956's avatar
Guy0956
Copper Contributor
Dec 29, 2022

EST, LST, EFT AND LFT

Hey, Can I add in MS Project to the network diagram the 4 times for any activity?  I mean: earliest start time, latest start time, earliest finish time and latest finish time   thanks  
  • John-project's avatar
    Dec 29, 2022

    Guy0956 

    You mean something like this?

    If so, select the Network Diagram view and then go to, Network Diagram Format > Format group > Format Box Styles. From there create your own template with the desired fields such as I've shown here: Note, for the label to show, click the "show label in cell box". For the data to show, do not click that box. (That may seem obvious but it took me a few minutes to figure out the "decoder key").

    Hope this helps.

    John

Resources