Enterprise Custom Field populated in PWA. Data is not populated in Desktop
I have created a resource Enterprise Custom Field called "Role". The new field shows up on the "Edit Resource" page in PWA. I populate the field with a value (it is a text lookup type using the "Role" lookup table). When I open the resource in Project Desktop, the field is there, but the value I entered in PWA is not there. It is just empty. If I update the value in the Desktop, it stays. Why is the value not showing up in the desktop when I populate through PWA?
Hello David_Howe ,
If you edit / update in PWA with MS Project desktop closed. Then launch MS Project Desktop, is the data then correct in MS Project Desktop?
Paul
Hello David_Howe ,
If you edit / update in PWA with MS Project desktop closed. Then launch MS Project Desktop, is the data then correct in MS Project Desktop?
Paul
- David_HoweCopper ContributorYes, Paul. Updating in PWA with desktop closed then opening after update, the data is there. Thanks so much for your help!
Happy to help, glad it is sorted David_Howe ,
Please can you mark my reply as the best response so it helps others who might have the same issue.