Forum Discussion
ware32
May 02, 2024Copper Contributor
disallow timesheet recovery
Is it possible to configure microsoft project server 2019 on premise to NOT allow users recovery the timesheets already approved by the project leader?
RodFromm
Steel Contributor
ware32- As Dale mentioned, there isn't a setting available to stop it. Nonetheless, closing past timesheet periods will prevent users from recalling the timesheet and altering it. It’s not a perfect solution, but it does stop users from changing previous timesheet submissions.
ware32
May 08, 2024Copper Contributor
I have located the option to close timesheets, but it could be possible to close timesheets for a specific project?