08-17-2020 12:19 PM
Good day
I've been trying to delete a resource that was initially deactivated (went back to school full-time) and later reactivated when he came back but I'm now realizing that his profile has errors. i tried deleting to reopen a new one but I cant seam to figure out a way to do that. Please help
08-17-2020 01:08 PM
Hi @Mpafane
It is always recommended not deleting resources from Project Web App as this can affect the reporting of actuals. Instead, deactivate resources that are no longer needed and reactivate back if required.
In case you would like to delete the resource, then below are the steps.
You won’t be able to delete the resource if the user/resource is any one of the following:
Hope this helps!
Kiran Khanvilkar