Forum Discussion
Paolone67
Apr 18, 2021Copper Contributor
Default views for PWA
Hi, I need to know if there is the possibility to set a view for PWA (e.g. Projects, Timesheet, Project details) as default view. Usually, when defining a view in SharePoint, the option to se...
Paul_Mather
MVP
Hello Paolone67 ,
Unfortunately this is not a feature available in Project Online PWA views, users will see the last view they used by default.
Paul
Paolone67
Apr 19, 2021Copper Contributor
Well but when I install PWA for the first time and the system does not know which is the last view a user used, what will PWA display as view? How can I discover which is the first view that is shown to a new user by the system? Thank you
Thank you.
Thank you.
- Apr 19, 2021Paolone67 --
There is a a default view that PWA displays when a user visits a page for the first time, but this is a system default view and NOT a view that the app admin can set for everyone. For example, the first time each user accesses the Project Center page, the system displays the Summary view by default. So, the answer is still no, it is not possible for the app admin to display the default view on each page in PWA. Hope this clarification helps.