Forum Discussion
Craigsquestions
Aug 17, 2022Copper Contributor
Datediff
Good day, I'm using project desktop. I used the the date diff formula to calculate the days left from now until the finish date of a task, but I want to know is there a way to use this formula o...
John-project
Aug 17, 2022Silver Contributor
Craigsquestions,
Yes, but you can't do it with a custom field formula since that formula can only reference data on a single task line.
However, with VBA, virtually anything can be done. If you can supply more details (e.g. how the 2 specific tasks are determined, are you looking for working days or calendar days, etc.), I can write some code for you.
John
Yes, but you can't do it with a custom field formula since that formula can only reference data on a single task line.
However, with VBA, virtually anything can be done. If you can supply more details (e.g. how the 2 specific tasks are determined, are you looking for working days or calendar days, etc.), I can write some code for you.
John