Oct 13 2021 04:31 AM
All,
Is it possible to highlight a start date or in my case many dates and up the date by intervals of dates? For Example, change all the following:
Mon 11/12/21
Tue 11/13/21
Wed 11/14/21
Highlight all and change date by 2 dates to result in:
Wed 11/14/21
Thurs 11/15/21
Fri 11/16/21
WayneF
Oct 13 2021 07:15 AM - edited Oct 13 2021 08:16 AM
Wayne,
Is it possible? Yes. Can it be done with some simple function in Project? No. You can either do it manually, or it could be done with some VBA.
However, I should ask what exactly are you trying to do? The simple example you give is a highly unlikely scenario for Project. If you could provide more definitive information, perhaps there's another approach that can get what you want/need.
John
Oct 13 2021 09:24 AM
SolutionOct 13 2021 09:48 AM
Oct 13 2021 09:24 AM
Solution