Forum Discussion

WayneDoubleu's avatar
WayneDoubleu
Copper Contributor
Oct 13, 2021
Solved

Date Update

All,   Is it possible to highlight a start date or in my case many dates and up the date by intervals of dates? For Example, change all the following:   Mon 11/12/21 Tue 11/13/21 Wed 11/14/21 ...
  • Dale_HowardMVP's avatar
    Oct 13, 2021
    Wayne --

    Yup, this is possible. Click the Task tab to display the Task ribbon. Select the tasks whose Start date you want to move. In the Tasks section of the Task ribbon, click the Move pick list button and select the Custom... item in the Move Task Forward section of the pick list. In the Move Task Forward dialog, enter 2d and then click the OK button. Microsoft Project will increase the Start date of only the selection tasks by 2 days. But keep in mind that in the process, the software will apply a Start No Earlier Than constraint on each of the tasks, and there is no way to prevent the software from doing so. Hope this helps.

Resources