Forum Discussion

Woody's avatar
Woody
Brass Contributor
Jun 20, 2024

Custom Scripts policy breaks editing Custom Fields in PDPs (Project Online)

Hi!

 

Due to the https://admin.microsoft.com/Adminportal/Home?#/MessageCenter/:/messages/MC714186 with the CEWP, we cannot edit Project Details Pages anymore to add/remove Enterprise Custom Fields in Project Online.

 

This should be working as Enterprise Custom Fields are not Custom Scripts!

 

Any advice?

 

Thanks in advance

14 Replies

  • RodFromm's avatar
    RodFromm
    Steel Contributor

    Woody In our tenant custom scripting must enabled to modify the PDP (web part) and I have recently modified a PDP.  Have you talked with your global sharepoint admin to see if they need adjust a policy or configuration in your tenant?

    • PaulB1810's avatar
      PaulB1810
      Copper Contributor
      I noticed the same change in my personal O365 Tenant as well. It looks pushed out by Microsoft vs a change from the work Project Online instance.
    • Woody's avatar
      Woody
      Brass Contributor

      RodFromm 

       

      What is the relation between adding or removing ECFs to a PDP and Custom Scripting? 

       

      I cannot see why a basic Project Online functionality is impacted by the recent Custom Scripting policy. We cannot work by opening a ticket to disable the policy every time we need to modify a PDP to add or remove a ECF with no use of Custom Scripts!

       

      Additionally, Site Collection Content Types are not editable anymore, so if you use a Word file as a template for CTs, you cannot edit it anymore.

       

      All due to the Custom Scripting policy.