Critical path in P4W
Hi All I can see that P4W does not support Critial Path https://support.microsoft.com/en-us/office/what-is-project-for-the-web-c19b2421-3c9d-4037-97c6-f66b6e1d2eb5, but I can see Critial Path by ...
Jan 01, 2023
daibt --
Critical Path is a feature that was added to Project for the Web in the last year or so. I suspect that the article you reference was written BEFORE the Critical Path feature was added to Project for the Web. Remember that this software is in continuous development, with new features being added every month or two. Hope this helps.
Critical Path is a feature that was added to Project for the Web in the last year or so. I suspect that the article you reference was written BEFORE the Critical Path feature was added to Project for the Web. Remember that this software is in continuous development, with new features being added every month or two. Hope this helps.
daibt
Jan 01, 2023Brass Contributor
- Paul_MatherJan 02, 2023MVP
Hey daibt,
To add to this, the Critical Path feature in P4W is available for users with Project Plan 3 or higher: https://learn.microsoft.com/en-us/office365/servicedescriptions/project-online-service-description/project-web-service-description#feature-availability
Paul
- daibtJan 02, 2023Brass Contributor
Thanks for your document, that help me to make sure that Project Plan 3, 5 support Critical Path only
- Paul_MatherJan 03, 2023MVP
You're welcome daibt , please mark a response as the answer when you get a chance so that it helps others.