%3CLINGO-SUB%20id%3D%22lingo-sub-2631123%22%20slang%3D%22en-US%22%3ECopying%20project%20in%20Project%20Online%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2631123%22%20slang%3D%22en-US%22%3E%3CP%3EIs%20there%20a%20way%20of%20duplicating%20an%20existing%20project%20in%20Project%20Online%3F%20I%20know%20its%20pretty%20straightforward%20in%20Project%20for%20Web%20but%20I%20don't%20seem%20to%20find%20any%20button%20in%20Online.%20Thanks%20%3A)%3C%2Fimg%3E%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-2631386%22%20slang%3D%22en-US%22%3ERe%3A%20Copying%20project%20in%20Project%20Online%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2631386%22%20slang%3D%22en-US%22%3E%3CP%3EHello%26nbsp%3B%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F1121231%22%20target%3D%22_blank%22%3E%40allyally123%3C%2FA%3E%26nbsp%3B%2C%3C%2FP%3E%0A%3CP%3EYou%20could%20open%20the%20project%20from%20Project%20Online%20in%20Project%20Desktop%20Client%20and%20use%20%22Save%20As%22%20then%20give%20it%20a%20new%20name%2C%20that%20will%20create%20a%20new%20project%20with%20that%20project%20you%20just%20opened.%3C%2FP%3E%0A%3CP%3EPaul%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Contributor

Is there a way of duplicating an existing project in Project Online? I know its pretty straightforward in Project for Web but I don't seem to find any button in Online. Thanks :)

1 Reply

Hello @allyally123 ,

You could open the project from Project Online in Project Desktop Client and use "Save As" then give it a new name, that will create a new project with that project you just opened.

Paul