Connect MS Project to multiple MS Planner plans
Hi, I am using a single MS Project file for overall management of multiple sub-projects. Can I connect the MS Project file to Multiple MS Planner plans?
bananajones
Nov 23, 2022Copper Contributor
Dale_HowardMVP - I am reviewing solutions for our EPMO and am interested in seeing this functionality. When you talk about project creating a hyperlink only and no interaction between them, would you be able to provide a visual of what you mean? I didn't quite follow.
Thank you,
Shanna
Nov 23, 2022
Shanna --
When you link a Planner plan to a task in an enterprise project, Microsoft Project displays an indicator in the Indicators column to the left of the task name. When you click on the indicator, Microsoft Project opens the plan in Planner. That is the extent of the interaction between these two tools. Make sense? Let me know.
When you link a Planner plan to a task in an enterprise project, Microsoft Project displays an indicator in the Indicators column to the left of the task name. When you click on the indicator, Microsoft Project opens the plan in Planner. That is the extent of the interaction between these two tools. Make sense? Let me know.