Configure a default view in Project
Hi!
We are testing Project in our work team. We are used to Planner; transition should go well.
We are using the web version of Project (in part because I can't find my Project created online in the Desktop version; in part because not all the team has a paid licence for now, but they must be able to access the tasks in the Planner-like views).
I have two main annoyances with Project so far.
First : I must refresh the page multiple times a day, which wasn't the case in Planner. If I don't refresh, I can't do anything; everything is greyed. And when I refresh, I lose all my filters.
I guess I can't solve the refresh issue, so I wonder if I can at least create a personalize default view, which includes all the filters I use 99% of the time, so at least, each time I refresh the page, I find back this view?
Thanks.
4 Replies
- RodFrommSteel Contributor
JoDio If you are using a Planner Premium in a named instance you can create custom views and change the default Project view. I haven't tried it, but you I would expect you can do the same for Programs and Project Requests views.
Set Default View - Select new default view, then click Set as default view
Create New Project View -
This requires familiarity with PowerApps and that you have the privileges to modify solutions.Use my advice below as reference only and try this in a test environment as your results may vary.
- Go to Power Apps Home page and select your environment
- Click Solutions
- Open the Ribbon - Customization solution
- Expand Tables, Project then select View
- Click + New view, enter Name and Description then click Create
- Add columns to view
- Set Sort by and Filters on the right
- Click Validate. Fix any report issues and revalidate
- Click Save and Publish
- Return to Power Apps Home page select Apps then open your Project app
- Click on Plans then open the view dropdown and the new view should be present.
- Rod --
Thanks for jumping in with your expertise on this problem!
- JoDi --
There is no way to configure a default View in Project for the Web. Sorry, but hope this helps.- JoDioCopper ContributorUnfortunate. Thank you.