Forum Discussion

ErikLevada's avatar
ErikLevada
Copper Contributor
Jul 09, 2022

Cannot import activity duration from excel

Hi All,

 

this is my first post because I just started to use MS Project. I'm Italian so sorry for my English (not traslated with Google😎).

 

When I try to import activities from a .xlsx file everything works properly but it doesn't import the activity duration also if it found the correspondance.

This is my data origin file:

This is correspondances found during import procedure:

And this is the result:

Can please someone help me?

 

Thanks in advance

Erik

 

2 Replies

  • Hi Erik You can try, before importing, to configure in Options (Schedule section): For all new projects, that New tasks created are scheduled automatically? If you need them to be manual, convert them later and delete the Start and Finish dates. I await your comments.
  • John-project's avatar
    John-project
    Silver Contributor
    Erik,
    It works for me and I don't see anything obvious in the process you used.

    The duration value imported to Project will be in the units that are set for the Duration field. For example, the default is "days" so the duration value from Excel will import as days in Project. If the Project option is set for Duration values to be in weeks, the duration value from Excel will import as weeks in Project. I don't recall if this is the case for previous version of Project.

    1. What version of Project are you using?
    2. What version of Office?
    3. Are both Project and Office fully updated?
    4. What units value do you have set for the Duration field (e.g. days, weeks, etc.)?
    John