Bulk Edit Not Working
I would like to bulk edit tasks, specifically the Task Calendar. I highlight multiple rows (2 or more), select Information -> Advanced -> Calendar and then pick a calendar, but no changes are ma...
- Sep 27, 2023All --
I have the same version of Microsoft Project that others are using. I just did an extensive test on the features in the Multiple Task Information dialog, and can confirm that NOTHING is working in this dialog. I tried changing the Duration for a block of tasks. No go. I tried changing the constraint type to As Soon as Possible to a block of tasks, each of which has a SNET constraint applied, and no go again. It is obvious that Microsoft has introduced a bug into Microsoft Project, and this bug NEEDS TO BE FIXED. I will report this bug to my contacts within Microsoft to see if they can get the fix moving. Thanks so much to all for reporting this.
Sep 27, 2023
All --
I have the same version of Microsoft Project that others are using. I just did an extensive test on the features in the Multiple Task Information dialog, and can confirm that NOTHING is working in this dialog. I tried changing the Duration for a block of tasks. No go. I tried changing the constraint type to As Soon as Possible to a block of tasks, each of which has a SNET constraint applied, and no go again. It is obvious that Microsoft has introduced a bug into Microsoft Project, and this bug NEEDS TO BE FIXED. I will report this bug to my contacts within Microsoft to see if they can get the fix moving. Thanks so much to all for reporting this.
I have the same version of Microsoft Project that others are using. I just did an extensive test on the features in the Multiple Task Information dialog, and can confirm that NOTHING is working in this dialog. I tried changing the Duration for a block of tasks. No go. I tried changing the constraint type to As Soon as Possible to a block of tasks, each of which has a SNET constraint applied, and no go again. It is obvious that Microsoft has introduced a bug into Microsoft Project, and this bug NEEDS TO BE FIXED. I will report this bug to my contacts within Microsoft to see if they can get the fix moving. Thanks so much to all for reporting this.
Kdekruif
Sep 28, 2023Copper Contributor
Dale,
Thank you for backing up my request to MS. I would definitely like to have this feature restored (Although it was nice to learn a new version of doing bulk edits from John.)
Thank you for backing up my request to MS. I would definitely like to have this feature restored (Although it was nice to learn a new version of doing bulk edits from John.)