Forum Discussion
Peter_ayad
Mar 30, 2023Copper Contributor
After receiveing tasks approval e-mail doesn't reflect on the MS Project online approval tab
Hello, I need your assistance as once the PM receives an email for a task update, it doesn't reflect on the approval page on the MS project online.
- Apr 02, 2023
Dale_HowardMVP Thanks a lot for your reply; I just wanted to update you that I found out that an outage on SharePoint caused this issue, and it is now resolved.
Mar 30, 2023
Peter --
What is your default Tracking method for your Project Online system? Was the update entered on the Tasks page or the Timesheet page in PWA? Has this resource previously submitted task updates that showed up on the Approval Center page?
Also, navigate to the Approval Center page and click the Manage Rules button in the ribbon. Do you have any auto-approval rules created for this project or this resource? Click the History button in the ribbon and select the Status Updates item on the menu. Do you see the update from this team member?
Let us know and we will try to help you.
What is your default Tracking method for your Project Online system? Was the update entered on the Tasks page or the Timesheet page in PWA? Has this resource previously submitted task updates that showed up on the Approval Center page?
Also, navigate to the Approval Center page and click the Manage Rules button in the ribbon. Do you have any auto-approval rules created for this project or this resource? Click the History button in the ribbon and select the Status Updates item on the menu. Do you see the update from this team member?
Let us know and we will try to help you.
- Peter_ayadApr 02, 2023Copper Contributor
Dale_HowardMVP Thanks a lot for your reply; I just wanted to update you that I found out that an outage on SharePoint caused this issue, and it is now resolved.