Forum Discussion
Floyds_on_Greenwood
Oct 26, 2020Brass Contributor
Add resources to a task that affect the duration of the task, but not the cost?
Objective: We would like to add resources to a task that affect the duration of the task, but not the cost. Constraints: Project costs cannot change up or down. Example: Task with multiple resource...
Floyds_on_Greenwood
Oct 28, 2020Brass Contributor
We captured the previous task work $$. Then changed the resource from work to cost for each task. The work resource $$ we captured previously was then added to the task as cost $$.