Forum Discussion

Clemay300's avatar
Clemay300
Copper Contributor
Apr 05, 2024

Actual Task Hours "Auto-populating" in Resource Timesheet

Hello!   I have a question about tasks that seem to have time actual values "auto-populate" in them on an employee's timesheets. Basically, when looking at a timesheet in Project Online (PWA), what...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Apr 06, 2024
    Cleymay300 --

    If the project manager opens the enterprise project in Microsoft Project, and then manually enters a % Complete value on a task with resources assigned to it, the software will automatically calculate the Actual Work for each resource assigned to the task. If the PM then publishes the project, the Actual Work will automatically show up on each resource's Timesheet page in PWA. Have you quizzed your PMs to determine whether any of them are doing what I just described? If they are, tell them to stop doing this, as it appears you want all progress to be entered from the Timesheet page in PWA. The only exception for your PMs is that they can manually mark the % Complete value to 100% on only Milestone tasks. Hope this helps.

Resources