Forum Discussion
Access Project Online from MS Project desktop
- Apr 21, 2020
Hi alwaysLearner ,
Project Online desktop client can still be used - just not for Project for the web projects. From that same article - see the text highlighted in red below:
"I use the Project Online desktop client. Can I still use it? Does it connect to Project for the web?
Yes, you can still use the Project Online desktop client, and we encourage you to try Project for the web when it meets your needs. See the Comparing Project for the web and the Project Online desktop client table below.
The Project Online desktop client doesn’t connect to Project for the web – as with all other future features, we will be evaluating this based on user feedback."
Paul
Hello Paul_Mather
Thanks a lot for the reply. Now it makes sense.
However, still I saw this page: https://support.office.com/en-us/article/project-for-the-web-and-project-online-desktop-client-2dd7583c-eb34-467f-bf63-607bdc816e20
There, it says: "I use the Project Online desktop client. Can I still use it? Does it connect to Project for the web?
Yes, you can still use the Project Online desktop client, and we encourage you to try Project for the web when it meets your needs."
Thanks in advance for the reply.
Hi alwaysLearner ,
Project Online desktop client can still be used - just not for Project for the web projects. From that same article - see the text highlighted in red below:
"I use the Project Online desktop client. Can I still use it? Does it connect to Project for the web?
Yes, you can still use the Project Online desktop client, and we encourage you to try Project for the web when it meets your needs. See the Comparing Project for the web and the Project Online desktop client table below.
The Project Online desktop client doesn’t connect to Project for the web – as with all other future features, we will be evaluating this based on user feedback."
Paul