Hello Planner users!
Planner recently added a "Bucket Chart" to the Charts page, and we're continuing to think about ways to improve this view. I've heard snippets of feedback regarding pain po...
Timothy Grim
Copper Contributor
Sean I did devise a way to do the % complete based on checklist items. That data does exist in what you can output via the Planner Preview connector in Flow.
Ian Bruckner
May 24, 2018Iron Contributor
Are you doing that with the assumption the tasks are close to equally weighted in either effort or duration and doing a straight up # tasks complete / total # of tasks?
- Timothy GrimMay 24, 2018Copper Contributor
As we create the checklist items - trying to split them equally since there is no time or effort fields yet. Those would be really nice to have in addition. Or the ability to pull items from the checklist name value - I have not seen a way in the connector to do that yet in Task Details. Only description is available so far.