% Complete vs Physical % Complete
Is there some way to make the % Complete field represent the Physical % Complete? That is to say for the % complete to only reflect the status in the work effort field regardless of the duration.
For example:
IF Total Effort = 10 hours & Completed Effort = 5 hours (as would remaining effort)
THEN % Compete =50%
REGARDLESS of whether the duration says 3 months.
Currently the automated calculations always factor in the duration and it's not what I'm after.
Cheers
- JPobukCopper ContributorI second this. It seems to be a redundant feature and not what I would expect "% complete" to be used for.