Aug 11 2020 09:40 AM
I created a new project in Planner using "Use an existing plan from this team". After it created the project, it named it with the same name as the original with a (1) after the name. I renamed the project and remove all of the existing tasks, since I wanted to start clean. However, it not only removed them from the new project but it also removed them from the original project I made the new one from. I think that that behavior is amazingly ridiculous, however... My question is: is there anyway to recover the deleted tasks from the original?
Aug 11 2020 01:09 PM
Aug 11 2020 01:44 PM
Adam, thanks for the reply. I get that now. My question is, is there anyway to recover the tasks that were deleted?
Aug 11 2020 02:08 PM
Aug 11 2020 02:11 PM
Not what I wanted to hear. That is a real miss in design. You do something, especially something like deleting, and not have a way back is a major miss.
Aug 11 2020 02:22 PM
SolutionNov 30 2021 09:27 AM