Forum Discussion
zimmo
Aug 11, 2020Copper Contributor
Creating a Project (Planner)
I created a new project in Planner using "Use an existing plan from this team". After it created the project, it named it with the same name as the original with a (1) after the name. I renamed the...
- Aug 11, 2020Yeah, it’s a missing feature for sure but I’m sure it’s coming! Please go vote here:
https://planner.uservoice.com/forums/330525-microsoft-planner-feedback-forum/suggestions/16060894-add-recycle-for-deleted-tasks-in-plan
Adam
Aug 11, 2020
Hi!
When you select “use from existing” you just add the same plan, hence deleting something from it will delete it everywhere else that plan is used. You can create a new one (the other option) or use the copy plan feature! Read my blog post about how to do this here:
https://www.avepoint.com/blog/manage/microsoft-planner-new-features/
Adam
When you select “use from existing” you just add the same plan, hence deleting something from it will delete it everywhere else that plan is used. You can create a new one (the other option) or use the copy plan feature! Read my blog post about how to do this here:
https://www.avepoint.com/blog/manage/microsoft-planner-new-features/
Adam
- zimmoAug 11, 2020Copper Contributor
Adam, thanks for the reply. I get that now. My question is, is there anyway to recover the tasks that were deleted?
- Aug 11, 2020Sorry, missed that last thing 🙂
No, you can’t unfortunately
Adam- zimmoAug 11, 2020Copper Contributor
Not what I wanted to hear. That is a real miss in design. You do something, especially something like deleting, and not have a way back is a major miss.