Gantt project planner

Please i need help on how to make the Gantt project planner template to exclude weekends and holidays from painting it. attached is the file.  

5 Replies

    • mesfinM's avatar
      mesfinM
      Copper Contributor

      SergeiBaklan 

      YES, let's say my plan starts on Tuesday, the plan duration is 6 days. I want the planner to exclude Saturday and Sunday, I tried the weekend function, but didn't work well for me.

    • mesfinM's avatar
      mesfinM
      Copper Contributor

      Thank you for your help

       

      on the excel you attached, the plan duration is 8 days but it only colored 6 days, I think the planner still considered Saturday and Sunday as a working day.  what I was looking for is to not consider Saturday and Sunday as a working day and also not to color Saturday and Sunday. 

      thank you thou 

      • NikolinoDE's avatar
        NikolinoDE
        Gold Contributor
        I only changed the conditional formatting, so that there is no color for the weekend, as you wished at the beginning.

        I wish you continued success in your project with Excel

        Nikolino
        I know I don't know anything (Socrates)