Writing Macros in MS Project

Hello Fellas, I have made a sheet comprising of different activities in execute-serial manner e.g
Activity no 1. Create excel sheets (Company A) finish date 2/2/22
Activity no 2. Create excel sheets (Company B) finish date 4/2/22

Now in some cases activity from Company A is finishing first like in above example. But in other cases activity from Company B is finishing first and Activity from company A is finishing later. E.g

Activity 3. Fill data in excel sheet (Company B) finish date 6/2/22
Activity 4. Fill data in excel sheet (Company A) finish date 8/2/22

I have like more than 1800 activities in my sheet. I just want to filter activities which are finishing later. Like if we take above 4 activities i want to make a filter which can filter out the activity which is finishing later by reading the name and date against it. Is it possible? I have very little knowledge about programming. Thats why i am not able to write a code which can perform this task. Seeking forward to any help at this forum. Thanks

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    Meesam 

    Unless I'm missing something, you do not need VBA. Careful structuring of your file with a simple filter and sort should get what you want. Given what you have presented, here is a suggested structure.

    Then set up this sort

    When applied, this is the result

    Does that work for you? If not, why not?

     

    John

    • Meesam's avatar
      Meesam
      Copper Contributor
      Sir, Thank you so much for replying. Actually my sheet is already made. And it has alot of activities like i described. Now as i want to see only those activities which are finishing later. Thats why i want to write a macro which can compare names of 2 activities identifying which one is from company A and which one is from B. After that filtering out the activity which is finishing later. I have alot of files like this. So making it automatic will help me alot.
      • John-project's avatar
        John-project
        Silver Contributor
        Meesam,
        It's still not clear that you need a macro to do what you want. However, for me to better understand what you have I'd like to take a look at your file and then decide the best approach. You can send the file to me at the address below. I will ask some questions.
        John
        jmacprojataticlouddotdotcom
        (remove obvious redundancies)