Working hours without update

Hello

As a newbie in Project app I am trying to change working hours.

In general option I changed default hours of start and finish (7 - 16)

but in Change working time window there are still old data:

I can't handle with it.

What should I do to update hours in Change working time window?

Thank you in advance

1 Reply

  • janunio --

    Change the working schedule shown on the Standard calendar to match the schedule you entered in the Project Options dialog. You need to specify the same schedule in both the Project Options dialog and in the Change Working Time dialog for your Standard calendar. Hope this helps.