Forum Discussion

dc_27's avatar
dc_27
Copper Contributor
Apr 26, 2023
Solved

Why might my resource be over allocated

I'm just going through the schedule to level my resources, and one is showing as overallocated on one week, when he isn't. and under allocated where he isn't.   I've checked to see if he had a pers...
  • John-project's avatar
    John-project
    Apr 26, 2023
    David,
    Max unit value isn't in hours per week, it is expressed as a percent or a decimal (i.e. 100%) for each resource on the Resource Sheet. Perhaps mean that resource max unit value is 31.6/40= 0.79 (i.e. 79%)?

    Change the Bottom Tier on the timescale to Days. Then look at the hours per day for that particular resource. You'll likely find a day when the resource is over the maximum.
    John

Resources