Forum Discussion

JBLT-77's avatar
JBLT-77
Iron Contributor
Jul 26, 2022
Solved

Why Does Project Change the Order of Task IDs in the Predecessor Column

I noticed that Project is changing the order of the task ID numbers listed in the predecessors column and I don't know why or if its a big deal or not, but for example, I have Task 76.   Then I enter the Finish To Start Predecessors Tasks 56,67,73.   However, Project reorders them to be 67, 56, 73.    Why is it doing this?

  • JBLT-77 

    As I recall the "re-ordering" done by Project has to do with the sequence that tasks were created, or something similar. But your question of whether it is a big deal has a simple answer, the order doesn't affect anything (i.e. no big deal).

     

    However as it turns out I actually wrote a macro to re-order the Predecessor field a few years ago in response to another user's consternation about the non-sequential order.

     

    John

    'Rev A - modified code to replace existing predecessors with numerically sorted predecessors
    ' Do not need to worry about successors, they automatically get sorted with predecessors
    'Macro written by John - Project
    Private str() As String
    Private t As Task
    Private TstStr As String, TempStr As String
    Private i As Integer, j As Integer, k As Integer, NumTsk As Integer
    Private lnktyp As Long
    Sub sequential_PredsSucc()

    NumTsk = ActiveProject.Tasks.count
    ReDim str(NumTsk)
    For Each t In ActiveProject.Tasks
    If Not t Is Nothing Then
    If t.Predecessors <> "" Then
    TstStr = t.Predecessors
    lnktyp = pjTaskPredecessors
    ArrayBldAndSort TstStr, lnktyp
    End If
    End If
    Next t
    MsgBox "Pred/Succ sorting complete", vbInformation
    End Sub
    'this routine builds a single dimensional array of predecessor
    ' and/or successor data, sorts the array(s) in
    ' numerical order and finally dumps it as a delimited string into
    ' extra task field Text1 (Preds) and/or Text2 (Succs)
    ' Rev A - does not use Text1 and Text2, sorted preds replace existing preds.
    Private Sub ArrayBldAndSort(TstStr, lnktyp)
    i = 1
    While InStr(TstStr, ",") > 0
    str(i) = Mid(TstStr, 1, InStr(TstStr, ",") - 1)
    TstStr = Mid(TstStr, InStr(TstStr, ",") + 1)
    i = i + 1
    Wend
    str(i) = TstStr
    'sort the array that was just built
    For j = 1 To i - 1
    For k = j + 1 To i
    If str(j) > str(k) Then
    TempStr = str(j)
    str(j) = str(k)
    str(k) = TempStr
    End If
    Next k
    Next j
    t.SetField lnktyp, ""
    t.SetField lnktyp, str(1)
    If i > 1 Then
    For j = 2 To i
    t.SetField lnktyp, t.GetField(lnktyp) & "," & str(j)
    Next j
    End If
    End Sub

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor

    JBLT-77 

    As I recall the "re-ordering" done by Project has to do with the sequence that tasks were created, or something similar. But your question of whether it is a big deal has a simple answer, the order doesn't affect anything (i.e. no big deal).

     

    However as it turns out I actually wrote a macro to re-order the Predecessor field a few years ago in response to another user's consternation about the non-sequential order.

     

    John

    'Rev A - modified code to replace existing predecessors with numerically sorted predecessors
    ' Do not need to worry about successors, they automatically get sorted with predecessors
    'Macro written by John - Project
    Private str() As String
    Private t As Task
    Private TstStr As String, TempStr As String
    Private i As Integer, j As Integer, k As Integer, NumTsk As Integer
    Private lnktyp As Long
    Sub sequential_PredsSucc()

    NumTsk = ActiveProject.Tasks.count
    ReDim str(NumTsk)
    For Each t In ActiveProject.Tasks
    If Not t Is Nothing Then
    If t.Predecessors <> "" Then
    TstStr = t.Predecessors
    lnktyp = pjTaskPredecessors
    ArrayBldAndSort TstStr, lnktyp
    End If
    End If
    Next t
    MsgBox "Pred/Succ sorting complete", vbInformation
    End Sub
    'this routine builds a single dimensional array of predecessor
    ' and/or successor data, sorts the array(s) in
    ' numerical order and finally dumps it as a delimited string into
    ' extra task field Text1 (Preds) and/or Text2 (Succs)
    ' Rev A - does not use Text1 and Text2, sorted preds replace existing preds.
    Private Sub ArrayBldAndSort(TstStr, lnktyp)
    i = 1
    While InStr(TstStr, ",") > 0
    str(i) = Mid(TstStr, 1, InStr(TstStr, ",") - 1)
    TstStr = Mid(TstStr, InStr(TstStr, ",") + 1)
    i = i + 1
    Wend
    str(i) = TstStr
    'sort the array that was just built
    For j = 1 To i - 1
    For k = j + 1 To i
    If str(j) > str(k) Then
    TempStr = str(j)
    str(j) = str(k)
    str(k) = TempStr
    End If
    Next k
    Next j
    t.SetField lnktyp, ""
    t.SetField lnktyp, str(1)
    If i > 1 Then
    For j = 2 To i
    t.SetField lnktyp, t.GetField(lnktyp) & "," & str(j)
    Next j
    End If
    End Sub