Why does each task take up an entire day, even if it's work-driven with an amount of work set at 1h?
I'm new to this. My tasks are auto-scheduled, and the ones in questions are work-driven, each with an amount of work set at one hour. I have my scheduling set to enter duration in hours, but they are...
John-project
Jan 04, 2021Silver Contributor
MSProjectNoob,
I'm not quite sure what you mean by "work-driven" but if you set it up properly your example should look like this
Note that in Project duration and work are two separate metrics. Duration is the time span during which a task is performed and work is the effort one or more resources will use to accomplish that task.
John