Why does each task take up an entire day, even if it's work-driven with an amount of work set at 1h?
I'm new to this. My tasks are auto-scheduled, and the ones in questions are work-driven, each with an amount of work set at one hour. I have my scheduling set to enter duration in hours, but they are...
Jan 04, 2021
The default Duration value for every task is 1 day. If you need the Duration to be 1 hour, you must manually enter 1h in the Duration column that the task in question. If you want to enter Duration values in hours, you can click File > Options > Schedule. About halfway down the Schedule page, change the value to Hours in the Duration is Entered In field, and then click the OK button.
Hope this helps.