Why do projects disappear from the Project Center when added to a Master Schedule?
- Jan 27, 2022JL Gregory --
What you are describing is a new feature that was added to the Project Center page in PWA some years ago. To my regret, I believe the new feature has caused people a bit too much confusion and heartache. By default, the Project Center is now configured to display only single projects and master projects, but NOT to display subprojects in a master project. To display the subprojects of a master project in the Project Center page, first expand the Projects ribbon. Then all you need to do is to click the Subprojects checkbox in the Show/Hide section of the Project ribbon. Voila! The subprojects will magically appear. Hope this helps.
What you are describing is a new feature that was added to the Project Center page in PWA some years ago. To my regret, I believe the new feature has caused people a bit too much confusion and heartache. By default, the Project Center is now configured to display only single projects and master projects, but NOT to display subprojects in a master project. To display the subprojects of a master project in the Project Center page, first expand the Projects ribbon. Then all you need to do is to click the Subprojects checkbox in the Show/Hide section of the Project ribbon. Voila! The subprojects will magically appear. Hope this helps.
- Jan 28, 2022JL --
I think your best bet for milestone reporting would be to create a Power BI report for milestones in each of the subprojects. Hope this helps.- JLGregoryIBMFeb 07, 2022Tin Contributor
Dale_HowardMVP, we followed through with your suggestion and looked into Power BI for Project Server reporting, however paying $50k / user per year is untenable, even for larger organizations --- if you have encountered any BI tools that are reasonably priced that are compatible with Project Server / SharePoint, please let me know. None of the out-of-the-box reports that come with Project Server are relevant to modern PM practices.
As you are probably aware, Project Server was designed without the input of industry leaders or program management SMEs, and even with the UMT acquisition, external reporting solutions are still mandatory. Clearly, Power BI Premium is not that solution for the majority of companies, from what I have heard at the conferences (due to the large function / price gap).
I'll be interested from hearing from other power EPM users regarding their experience with advanced portfolio reporting using Project Server. Hopefully, we will be able to find a viable solution with Excel Reporting Services, though I am doubtful it will be viable without extensive custom dev.