When inserting subprojects from Enterprise projects, it shows current AND deleted projects?

Hi there, 

 

When I try to insert a subproject in the Project Professional desktop app, it shows all enterprise projects ever created, even ones that have been deleted. 

I have to double click on "Show me the list of all projects" to get a list of the current live projects, which matches with the list of projects shown when on the PWA - Delete Enterprise Objects page (excluding templates)

 

Is there any way to remove all the deleted projects from the "Enterprise Projects" list when trying to insert a subproject without having to click on "Show me the list of all projects?"

 

  • Hello BlissL ,

    This will be from the local Project cache, you would need to remove the deleted projects from your local cache.

    Paul