Forum Discussion

Pantelis_Natsiavas's avatar
Pantelis_Natsiavas
Copper Contributor
Oct 29, 2021
Solved

When a task is completed for x%, can it be planned only for the (100-x)%?

I use Microsoft Project Professional 2019 and I have "Task A" (type "Fixed Units", Effort Driven) which has a whole duration of 10 days and at the day of planning is completed at 70%. As far as I can...
  • John-project's avatar
    John-project
    Nov 02, 2021

    Pantelis_Natsiavas 

    In light of the alternate scenario (i.e. one resource working the task full time for the first 7 days and then another resource finishing the task working half time), I think the easiest approach is to separate the task into two parts.

    1. Set up the first part as the full task of 10 days with 80 hours work and assign the full time resource. Enter 70% into the % Complete (or % Work Complete) field. Make a note of the remaining work, it should be 24 hours.

     

    2. Create the second part (i.e. task b). The duration will default at 1 day. Enter the remaining work from the first part (i.e. 24 hours) into the Work field. Assign the half time resource. The task duration should expand to 6 days.

     

    3. Edit the Work field for task a (the first part) to the existing actual work value (i.e. 56 hours). The Percent Complete should go to 100%. That captures the task effort completed by the first resource.

     

    This process works whether the tasks are set to Fixed Work or Fixed Units and it should give the end result you need.

     

    There are other ways to get this same result but I believe this is the easiest and most straight forward.

    John

Resources