What Project Views, Tables or Fields Can Give Me Insight Into How Far Ahead or Behind The Project is

I have the earned value report and table that just tells me visually or in monetary terms whether my project is ahead, on schedule or behind schedule, but I'm looking for a view, report or table that tells me quantitively in Duration how much tasks and the project overall is ahead or behind schedule.  

 

I thought maybe the Variance table might help but the variance fields are all based on plan against baseline and my planned dates are usually the same as my baseline dates. I would think that variance based on comparing planned/baseline vs. actuals would be more accurate in whether a project is ahead or behind schedule.

 

I want to be able to answer the question How many days/weeks is my project  ahead/on/behind schedule?

 

Any suggestions?

  • JBLT83 --

    I would recommend you use the Tracking Gantt view with the Variance table applied. Please be aware that the Variance table is NOT showing planned versus baseline. The values in the Start Variance and Finish Variance columns show planned and actuals versus the baseline. If you are seeing 0d values in these two columns, that indicates your project is on schedule. Then again, how are you entering progress in your projects? I personally recommend using a modified version of the Tracking table in which I can enter updates for each task using the following columns:

    Actual Start
    % Complete
    Remaining Duration
    Actual Finish

    If you modify your Tracking table as shown above, this will give you a "date sensitive" method for tracking progress, which would potentially reveal variance in the Variance table. Just a few thoughts. Hope this helps.

4 Replies

  • JBLT83 --

    I would recommend you use the Tracking Gantt view with the Variance table applied. Please be aware that the Variance table is NOT showing planned versus baseline. The values in the Start Variance and Finish Variance columns show planned and actuals versus the baseline. If you are seeing 0d values in these two columns, that indicates your project is on schedule. Then again, how are you entering progress in your projects? I personally recommend using a modified version of the Tracking table in which I can enter updates for each task using the following columns:

    Actual Start
    % Complete
    Remaining Duration
    Actual Finish

    If you modify your Tracking table as shown above, this will give you a "date sensitive" method for tracking progress, which would potentially reveal variance in the Variance table. Just a few thoughts. Hope this helps.
    • JBLT-77's avatar
      JBLT-77
      Iron Contributor

      Dale_HowardMVP How do the Start Variance and Finish Variance use Actuals?  According to MS Project the variance fields are Start-Baseline Start and Finish-Baseline finish.  If actuals were used these fields should be using Actual Start and Actual Finish.

       

      As far as how I enter my progress, when a task reached the "In Development" bucket, I set % Complete to 25%, when it gets to Ready for System Testing and System Testing I updated to 50%, Ready for UAT and UAT, 75%, and when its ready for production % completed=100

      • JBLT83 --

        When a task has an Actual Start date, Microsoft Project copies the Actual Start date into the Start field. When a task has an Actual Finish date, Microsoft Project copies the Actual Finish date into the Finish field.

        If your tracking method is simply entering a % Complete value, then you will never be able to see late Starts or late Finishes, which means you will never see Start Variance and Finish Variance values other than 0 days. For example, Task A was supposed to start on Monday, but it did not actually start until Wednesday of that week. How would you enter progress on the task in this situation? This is why I recommend you begin using the modified version of the Tracking table so that you can enter Actual Start dates and Actual Finish dates.

        Hope this helps.