Forum Discussion

SPQR1965's avatar
SPQR1965
Copper Contributor
May 14, 2024
Solved

What is the best way to update actuals against MS Project Tasks?

We are currently working with PWA and Microsoft Project Professional. We conduct all of our estimates in hours and task contributors advise of progress by providing hours progress against each task. ...
  • John-project's avatar
    May 14, 2024
    SPQR1965,
    It depends on whether you want to track the total actual hours or timebased actuals. Total actual hours can be entered via the Actual Work field of the Gantt Chart, Task Usage, or Task Sheet views. Make sure you also review and change, if appropriate, the Remain Work field.

    However, if you need/want to enter assignment actual work for each reporting period (i.e. day, week, month), then that data should be entered directly into the timescale grid Actual Work for each assignment (task or resource). However note that Remaining Work is not available in the timescale grid, that value would be entered under the Remaining Work field static data (left side of view). Project will automatically spread it across the remaining period in the timescale data as Cumulative Actual Work.

    Hope this helps.
    John

Resources