What is in the lead: The Calender or Project-Options Calendar settings in MS Project Pro?
Description Within MS Project you can set the calendar options (File – Options – Planning – Calendar Options). This can then be done for specific projects or for all new projects. I change the set...
John-project
Apr 22, 2021Silver Contributor
Let me add one more thing to Dale's excellent reply. When customizing the Project Calendar, new users often tend to edit the default Standard calendar but that's not a good idea. Rather, if the user needs a custom calendar, it is best practice to create a new calendar, perhaps based on the Standard, with the working days and shift times as needed. The preserves the integrity of the Standard calendar.
John
John
Hans_Fransen
Apr 23, 2021Copper Contributor
- John-projectApr 23, 2021Silver ContributorHans,
You're welcome and thanks for the feedback. Please consider marking Dale's response as the answer to your question, I only provided a small supplement.