Forum Discussion
Per_Alm
Jan 27, 2023Tin Contributor
What happens when moving a task in the task list?
Hi, Sorry for a "stupid" question from a newbie: Tasks can be drag and dropped in the task list. When doing this they will change their task-ID to the new number of the row. In addition, also oth...
- Jan 27, 2023Per_Alm --
Using drag and drop to move tasks will not cause any harm in your projects. I have used this technique for decades without a problem. Yes, when you drag and drop tasks, Microsoft Project DOES renumber the tasks. However, what you probably do not know is that there is a hidden ID number that DOES NOT ever change, which is called the Unique ID. Insert that column and then try drag and drop. Microsoft Project uses the Unique ID numbers to maintain the task links. Hope this helps.
Jan 27, 2023
Per_Alm --
Using drag and drop to move tasks will not cause any harm in your projects. I have used this technique for decades without a problem. Yes, when you drag and drop tasks, Microsoft Project DOES renumber the tasks. However, what you probably do not know is that there is a hidden ID number that DOES NOT ever change, which is called the Unique ID. Insert that column and then try drag and drop. Microsoft Project uses the Unique ID numbers to maintain the task links. Hope this helps.
Using drag and drop to move tasks will not cause any harm in your projects. I have used this technique for decades without a problem. Yes, when you drag and drop tasks, Microsoft Project DOES renumber the tasks. However, what you probably do not know is that there is a hidden ID number that DOES NOT ever change, which is called the Unique ID. Insert that column and then try drag and drop. Microsoft Project uses the Unique ID numbers to maintain the task links. Hope this helps.
- Per_AlmJan 27, 2023Tin ContributorThanks a lot, this explain things! I was thinking that the ID number should be unique, I was not aware that there was an additional "unique ID". And, I now noticed that I was wrong: the non-unique predecessor number does update, it was just that my test moves did not require updates. Thanks Dale!
- Jan 27, 2023Per_Alm --
What a nice response, my friend! You are more than welcome for the help. BTW, if my reply answers your question, would you please mark my post as the best response? Thanks!