What algorithm does MS Project use when calculating BCWP
Hello Gilgamesh1964 ,
Here is the article on how BCWP is calculated: https://support.microsoft.com/en-us/office/bcwp-earned-value-or-ev-fields-e0c570ea-9c7b-4864-8a6b-920ed0f7b847
Paul
Thank you for responding but I am getting some results that don't align with that description.
(I hope you are able to read the attached images)
These two tasks were identical when baselined, it is the actuals and remaining work forecast that differs.
I believe the top one is behaving as per that description you referred to, but I would expect the bottom one to have a BCWP of $5.50 rather than $5.61.
This was done with:
Microsoft Project Online Desktop Client MSO (16.0.14326.20936) 64-bit
Version 2108 (Build 14326.20962 Click -to-run)
(This is from the Semi-Annual Enterprise Chanel)
It was getting this result that lead to my initial post. ![]()
I repeated the same test with
Version 2204 (Build 15128.20248)
Microsoft Project 2016 MSO (Version 2204 Build 16.0.15128.20240) 64-bit.
(My home version of MSP 2016 Professional)
With this second test I get the expected result of $5.50 on the second task.
Is this a bug with the Microsoft Project Online Desktop version?