Were you able to retrieve the Resource Name value in Power automate? Need help
I am seeking a way to retrieve the Resource Names (from the project online) in Power Automate, where I can use the respective email IDs to send out an automatic email for the respective task assigned...
Paul_Mather
Jan 12, 2024MVP
Hello Geetha_R ,
What endpoint are using using in the Odata API within your Power Automate flow? The ResourceName property is in the Assignments and ResourceDemandTimephasedData endpoints, have you used these? To get the ResourceEmailAddress you'd need to use the Resources endpoint, you can join to this using the ResourceID property.
Paul
Geetha_R
Feb 09, 2024Copper Contributor
Paul_Mather Thankyou for responding to our query, could you please guide us more on this?
- Paul_MatherFeb 09, 2024MVP
Hello Geetha_R ,
I think we'd need to understand more details to help further. Did the first reply not help you get the Resource Name?
Paul