Forum Discussion

shiromeri's avatar
shiromeri
Copper Contributor
May 17, 2021
Solved

Web Project - Select a default view when opening the resource page

Hello, The resource site on PWA 2013 remembers the last view that I had, however it is requested to always open up a default view and not the last selected one.   Can anyone help with this?   T...
  • Paul_Mather's avatar
    May 18, 2021

    Hello shiromeri ,

    The PWA views will always open the last view the user went to. There are default system views that will be used for a new user who has not accessed the page / view before but you are not able to change what view is classed the default system view.

    Paul