Forum Discussion

khyron's avatar
khyron
Brass Contributor
Aug 09, 2020

We can't display the selected time period. It might be closed or your administrator hasn't created..

Hi guys


I keep getting this when I or another colleague tries to complete a timesheet on Online

 

We can't display the selected time period. It might be closed or your administrator hasn't created it yet. Please try a different date.

 

What is the issue?

1 Reply

  • khyron 

    Hi,

    When you click on timesheet in the left navigation, Project Online creates the timesheet for the current timeperiod. Could you please check if timesheet period is available. Below are the steps.

     

    • Go to PWA Settings.
    • Click on Time Reporting Period.

    Check if the timesheet period is available for current timeperiod.

     

    Thank you,

    Kiran Khanvilkar