Visibility on the completed task in the past period (week/2 weeks/month)

Hi, 

We are on MS Project for the web. I'd like to have a visibility on the tasks that were completed by each team member in the past days, week, 2 weeks, month. 

Is there a way to do so on MS Project for the web? Or on any other tool? 

Thanks in advance for your support. 

Mélanie

1 Reply

  • MelanieBD --

    Although Project for the Web has some built-in filters to view tasks in the future, it offers no built-in filters for viewing completed tasks in the past within a specific time period. If you were using the Microsoft Project desktop application instead, you could use the AutoFilter feature with the Actual Finish column. The AutoFilter feature includes built-in filters including Yesterday, Last Week, Last Month, Last Quarter, and Last Year. There is also a Between option where you can specify the start and end dates of the filtering period and Microsoft Project will show you the completed tasks that actually finished during the time period you select.

    Just a thought. Hope this helps.