Forum Discussion

NancyDEMERS's avatar
NancyDEMERS
Copper Contributor
Mar 01, 2022
Solved

View Project online and Project in MS Teams

Can we see a Project that is in project.microsoft.com in MS Teams, Dynamics and project online? Can we change where we see it?   If I created a project in MS Teams project, can I see it Online as w...
  • Paul_Mather's avatar
    Mar 01, 2022

    Hello NancyDEMERS ,

    Project for the web projects can be view at project.microsoft.com, in MS Teams and in the Power Apps Project app (or custom App). Out of the box these projects cannot be seen in Project Online - Project Web App.

    Projects created in the "Project" app for MS Teams are Project for the web projects - out of the box these cannot be seen in Project Online - Project Web App.

    I hope that helps.

    Paul