VBA. Получение содержимого заметок к задаче в формате RTF
Коллеги! Добрый день! Подскажите, как в коде VBA можно получить содержимое заметок к задаче в формате RTF, т.е. с учетом форматирования и внедренных объектов? * Файл формата MPP, MS Project 201...
OldMike
Aug 27, 2021Copper Contributor
Thank you for your answer, John!
Can you give me advice, how to extract and write formatted notes to an MPP file in another way. From your point of view, is there such a possibility?
* The fact is that, I programmatically (VBA, Task (...). Notes) make changes to notes and after that the formatting is removed. I would like to fix this.
Thanks.
Can you give me advice, how to extract and write formatted notes to an MPP file in another way. From your point of view, is there such a possibility?
* The fact is that, I programmatically (VBA, Task (...). Notes) make changes to notes and after that the formatting is removed. I would like to fix this.
Thanks.
John-project
Aug 27, 2021Silver Contributor
OldMIke,
As far as I know there is no way to retain or capture Notes field formatting. Several years ago I faced the same issue and after talking to a contact at Microsoft I found out the notes text string is saved in more than one place in Project's underlying database, however when using VBA to capture the notes text, the un-formatted text string is what is captured.
It may be possible to use an API (or some other query) to get the formatted notes string out of Project's database but I have no idea how to do that.
John
As far as I know there is no way to retain or capture Notes field formatting. Several years ago I faced the same issue and after talking to a contact at Microsoft I found out the notes text string is saved in more than one place in Project's underlying database, however when using VBA to capture the notes text, the un-formatted text string is what is captured.
It may be possible to use an API (or some other query) to get the formatted notes string out of Project's database but I have no idea how to do that.
John
- OldMikeAug 27, 2021Copper ContributorThank you again!
I will "dig" further, if I find it, I will write (I hope, I will not forget).