Vacation in MS Project
Hi, I'm, struggling with vacations in MS Project. When I' inserting vacations in "insert working time", this is gone when I close the program and open it again. Does anyone here knows what Im doing w...
- Mar 10, 2023
When you mentioned vacations I assumed you meant time off for individual resources as that is what we in the US call a vacation. But it sounds like you are really talking about country/company holidays which apply to all resources.
To set up a custom calendar, first create a new calendar, perhaps based on the Standard, as I show here. I've also edited the work week to show work hours from 7:00 to 16:00 with a hour for lunch break.
Then I added a company summer shut down week in July. As as many exceptions as needed to cover the current and future years.
Hope that helps to get you started.
John
Mar 09, 2023
HaakonFS --
We want to help you, my friend, but you are leaving us guessing for lack of supporting information. Would you be able to post some screenshots of what you are trying to do? That would help us to troubleshoot and resolve your problem. Thanks!
We want to help you, my friend, but you are leaving us guessing for lack of supporting information. Would you be able to post some screenshots of what you are trying to do? That would help us to troubleshoot and resolve your problem. Thanks!