Forum Discussion
Alison Howes
Jul 06, 2023Copper Contributor
Using Timesheets in PWA but how to prevent changes to forecast
Hello Guys, I have a customer that is using Project Online. They are using Timesheets for capturing actuals and they want those actuals to be reflected in the original project. However they do n...
RatanPushp
Jul 12, 2023Brass Contributor
Better to set baseline in a project to keep forecast intact and rename baseline columns. After timesheet submission, the actuals and forecast can be referred.
Hope this helps you!